The standard elevator system (described previously for the first level) could not accommodate the exceptional size and weight of the megalithic blocks used in the King’s Chamber:
-
“Ordinary” blocks: ranging from 3 to 27 tonnes, manageable with the second-level elevator system.
-
Beams of the five ceilings and the gabled roof:
-
At 49 m: first ceiling of the chamber, with the heaviest beam weighing 70 tonnes.
-
At 62 m: final gabled roof, with the heaviest chevron weighing approximately 60 tonnes.
-
2. Limitations of the Standard System
-
First-level float (32 tonnes empty):
-
Draft: 8 m empty, 25.5 m when loaded with 70 tonnes.
-
In loaded condition, static equilibrium is reached at only 14.5 m—far below the required 49 m.
-
-
Second-level float:
-
Weighing 20 tonnes. When loaded with such a beam, it would protrude only 1 meter from the shaft—rendering it unusable.
-
3. Innovative Solution: Modified Hydraulic Circuit
Key configuration:
-
Intake reservoir: Confirmed by the ScanPyramids mission, located at the 20-meter level.
-
Filling: via a bucket chain passing through the “notched lintel,” which could be sealed watertight.
-
Draining: facilitated by an opening discovered by G. Dormion (fifth lintel of the descending corridor).
-
Water level optimization:
-
The presence of a 3-block plug at the beginning of the ascending corridor suggests a special scenario for lifting megaliths.
By opening this plug, the water circuits of the cave and the “Queen’s Chamber” could be combined:
-
Maximum water level would rise from 3 m to 23 m (the level of the Queen’s Chamber).
-
The top of the shaft at 3 m (first level) would then need to be sealed. This could be achieved by making the float’s movement watertight, for example using a waterproof textile “sleeve” around the float
-
.
Advantages:
-
Static equilibrium of the loaded float rises from 14.5 m to 34.5 m, a significant improvement.
-
However, this remains insufficient for the 49 m target—an additional 14.5 m are still required.
-
Safety margin preserved: 2.5 m of float remaining inside the shaft.
4. Two-Phase Procedure with Elevation Extension
Phase 1 – Preparation:
-
Complete drainage of the circuit.
-
Loading the beam onto the platform.
-
Refilling up to 23 m (via the intake reservoir and possibly supplemented by the basin).
-
Installation of anti-return chocks at 34.5 m to lock the platform in place with its load.
Phase 2 – Elevation:
-
New drainage cycle.
-
Installation of a modular extension (e.g., four 4-meter sections for a total of 16 m).
-
Second filling → elevation up to 49 m → immobilization with anti-return chocks.
-
Final drainage followed by beam unloading.
Adaptability:
-
Extension height is modular (e.g., 30 m for a 60-ton chevron placed at 62 m).
-
Precise adjustment of water level based on block weight and target height (e.g., N = 22.5 m for 60 t at 62 m).
5. Efficiency and Archaeological Evidence
-
Draining is straightforward using a bucket chain but relatively slow: approximately 56 m³ per day (for 10 hours of work).
-
Each fill-drain cycle would take 2 to 3 days—acceptable, considering only ~100 megaliths required lifting over the entire construction.
Confirmed traces:
-
Intake reservoir (confirmed by ScanPyramids).
-

Scan pyramids -
Specific lintel configuration (Dormion’s observations).

-
Plug in the ascending corrid
