To hoist a 70-ton block up a 52° slope, a force of 560 kN is required, which would have necessitated at least two ropes with a diameter of approximately 100 to 120 mm. Such ropes would have been too heavy for the required lengths and extremely difficult to handle.
As a result, for blocks exceeding 7 tons, the builders abandoned the idea of hoisting them along the pyramid’s faces.
Two potential solutions presented themselves:
The first was to build a temporary ramp reaching up to 62 m in height, the placement height of the last megaliths.
The second was to construct hydraulic float elevators at the center of the pyramid, as suggested by the configuration of the galleries and chambers found inside. This option is not discussed in this article but can be explored here:
Temporary Ramp

This external ramp would have been built progressively, maintaining the same slope from the same starting point as the pyramid rose, ultimately reaching a height of 64 m, the level of the top of the five “relieving chambers” above the “King’s Chamber,” which are made of megalithic beams and rafters, the heaviest of which could weigh up to 70 tons.
At its peak, this ramp started from the eastern facing of course #81 at 64 m above the base and extended to its origin point, the arrival of the causeway connecting the upper and lower temples at the plateau level, 6 m below the base, resulting in a 70 m elevation over a 350 m length, giving a 20% slope.
With this slope, the resistance to hoisting a block was reduced to 20% of its weight, compared to 80% along the pyramid’s face.
Thus, for the largest 70-ton blocks, which needed to be raised to 48 m, the ramp’s slope required a force of 140 kN. Two hemp ropes with a 44 mm diameter pulling in parallel would have been sufficient for the task.
One might think that using the same method as along the faces—two parallel lines of “dynamic ballast” consisting of 70 operators each, spanning 35 m—could have worked.
However, given the operational risks of suspending so many people on these ropes, the builders likely implemented a differential winch on the course between the operators and the load, with, for example, a gear ratio of ten.

This winch would have reduced the number of operators by a factor of ten, requiring only two lines of 7 operators in a dynamic ballast position or 26 operators in two lines of 13 pulling from the course.
The hoisting speed would have been reduced by a factor of ten, but since the number of these megalithic blocks was limited, this would have been acceptable without jeopardizing the construction schedule.
Change of Slope
When transitioning from an 8% slope to a 20% slope, without proper adaptations, the block suddenly encounters significant resistance because the water cushions become ineffective.
To ensure the block remains in constant contact with its cushions, it was necessary to place it on a slab that could pivot from an 8% slope to a 20% slope, allowing the block to change incline while staying in contact with the ground.
To achieve this, at the point of slope change, the builders could have created a pit slightly longer than the block, about 4 m wide and 1 m deep.
At the bottom of the pit, a step could be placed, occupying half the pit’s length, and an 8 m-long slab could be positioned on this step at its midpoint.

This slab would rest on the step, with a wedge at its downstream end to prevent it from tilting backward.
In this position, its slope is 8%, and the downstream part of the slab is flush with the causeway.
Thus, the beam can engage onto the slab at the end of its journey on the first part of the causeway.

Once the beam is fully engaged on the slab, the downstream part of the slab is unloaded, allowing the wedges to be removed. The beam can then be slightly backed up, causing the slab to tilt downstream to a 20% slope. Wedges can then be placed upstream of the slab to secure its position.

The beam is now on a 20% slope at the level of the temporary ramp and can continue its ascent.
Placement of a Beam
The placement of the beams for the ceilings of the “King’s Chamber” could begin when the course on which the chamber’s walls were flush was more than half-filled on the south and west sides, leaving a straight path for the beam, which would be positioned almost at the center of the pyramid.
The courses intended to receive these megaliths typically measure over 120 m in length, providing a large working surface.
The fixed frame on which the drum rolls could be 10 to 20 m long.
To exert the required force, operators could pull from a fixed position on the course, with their feet firmly planted, each exerting a force of 600 N.
Thus, a group of 13 operators per line (each line measuring 5 m) is sufficient to hoist a 70-ton beam to the 64 m course via the 20% temporary ramp, thanks to the differential winch.
Such a setup could be installed in a 20 m space on a course over 120 m long.
The large beams arrive on the course via the eastern face, approximately 30 m south of the central axis. Once on the course, the beam can be moved with little effort on its cushions toward the walls of the King’s Chamber, which are flush.
The beam could then engage in the east-west axis over the chamber’s walls, spanning the void.
For the final meter of the journey, the cushions were no longer placed in front of the beam, which then completed its path by sliding directly on the granite walls already coated with mortar.
With a friction coefficient of about 0.5, the maximum effort required to move the largest beam is 350 kN.
In this case, a differential winch could be placed west of the chamber in the east-west axis of the pyramid, with a gear ratio of 50.
Although the beam moves very slowly, it only has to cover one meter, and the force required from the team of operators is reduced to just 7 kN.
















